Ideal Foundations are half way through installing 1200 above ground screw piers supporting transportable admin buildings. The project is the construction of new admin buildings to support the building of a new Jail in Wellington NSW. The installation of the screw piers to support transportables above will take approximately three months Dec 2016 to Feb 2017. On average the screw piers are screwed down to 3.75m to accomodate the potential movement of the reactive soils on the site.
We’d like to thank Modular Building Systems (MBS) for the opportunity for our screw piers to support their transportable buildings. A project on this scale certainly makes our screw piers protruding from the ground look like soldiers marching – anyway we think so 🙂
It’s also a pleasure to work on a well planned construction – awesome work Hansen & Yunken!