A builder who knows his numbers are fixed!
Foundation work has just started on a set of 33 two storey units in Camden South, South West of Sydney. The builder/developer is also currently completing another project where the Ideal Foundations team installed screw piers for a 22 unit project in Oran Park. The speed in which they got out of the ground on the previous site was one of the defining reasons to do same on the their new 33 unit project plus the added bonus of having their foundation costs fixed.
Like the previous site Ideal Foundations assisted in their redesign away from bored concrete piers to screw piers. This was achieved by conducting a thorough geotechnical report across the site which also enabled Ideal’s engineer’s to determine founding depth and fix the cost of foundations. The geotechnical report also identified acid sulphate soil, which means the screw piers will be core filled with concrete for the required design life.
Here’s what the numbers look like:
All this at a fixed price.